Fiscal Note
In the adopted 2017 capital budget Engineering-Major Streets has budgeted $7.87 million for the replacement of deteriorated streets via the Reconstruction Streets major program (MUNIS 10226). The minor project for the N. Basset Street and Conklin Place reconstruction is established with sufficient authority for the planned project (MUNIS 11430). The proposed resolution approves plan documents at a total estimated cost of $1,892,000. Funding is provided by GO Borrowing, Assessments, and associated Utility funding.
MUNIS:
11430-83-173 Sewer: $567,000
11430-84-174 Storm: $175,000
11430-86-179 Water: $200,000
11430-402-170 Major Streets: $700,000
11430-402-174 Major Streets: $50,000
11430-402-176 Major Streets: $104,000
11430-402-177 Major Streets: $96,000
Title
Approving Plans, Specifications, And Schedule Of Assessments For North Bassett Street, Conklin-University Alley, and Henry-Broom Alley Assessment District - 2017.
Body
The Board of Public Works and the City Engineer having made reports of all proceedings in relation to the improvement of North Bassett Street, Conklin-University Alley, and Henry-Broom Alley Assessment District - 2017 pursuant to a resolution of the Common Council, RES-17-00085, ID No. 45523, adopted 1/17/2017, which resolution was adopted thereto, and the provisions of the Madison General Ordinances and the Wisconsin Statutes in such case made and provided, and the Common Council being fully advised.
BE IT RESOLVED:
1. That the City at large is justly chargeable with and shall pay the sum of $1,689,552 of the entire cost of said improvement.
2. That for those eligible property owners requesting construction of a rain garden in the public right-of-way adjacent to their property shall execute the necessary waiver of special assessments on forms provided by the City Engineer;
3. That the sum assigned to each separate parcel, as indicated on the attached schedule of assessment, is hereby specially assessed upon ea...