Fiscal Note
The proposed resolution amends the 2017 Adopted Capital Budget within Engineering-Major Streets by transferring $140,000 of GO Borrowing budget authority from the Mckee Road (CTH PD) project (MUNIS10245) to the East Johnson Street (Baldwin to 1st St.) (MUNIS 10287) to provide funding for design services in accordance with the amended contract on the East Johnson Street project.
The McKee Road Improvement project is anticipated to be completed in 2017 with sufficient unspent appropriation to allow for the $140,000 of GO Borrowing to be moved to the East Johnson Street project for the additional design costs.
MUNIS:
10287-402-170 $140,000
10287-402-801 ($140,000)
10245-402-170 ($140,000)
10245-402-801 $140,000
Title
Approving the roadway geometry for East Johnson Street from Baldwin Street to First Street (2nd and 12th AD), authorizing to execute an Amendment to the contract with the design consultant, and Amending the 2017 Engineering Major Streets Capital Budget to transfer $140,000 of GO Borrowing from the Mckee Road (CTH PD) Improvements project to the East Johnson Street: Baldwin to 1st Street project.
Body
The City of Madison and Strand Associates Inc entered into an agreement for design engineering services (Original: RES-15-00183) for the reconstruction of East Johnson Street from Baldwin Street to First Street.
The proposed project consists of reconstructing East Johnson Street between North Baldwin Street and North First Street to provide new pavement, curb and gutter, widening along the west side of N. First Street, bike/pedestrian accommodations and existing sidewalk spot replacements/repairs. As part of the reconstruction, sanitary sewer, water main, storm sewer laterals and inlets, street lighting and traffic signals will be replaced. Continuous bike/pedestrian accommodations will be provided through a combination of sidewalk and existing/proposed multiuse paths for the length of the project.
The project is ...
Click here for full text