Fiscal Note
The total estimated cost of the signal installation is $131,941.63. Funds for the City's share of $77,362.93 are available in the Traffic Engineering's 2017 Capital Budget Packers-Darwin Traffic Signal Assement Project (Munis 17449). Legistar File 46372 amended Traffic Engineering’s 2017 Capital Budget for the remaining assessable costs of $54,578.70.
Title
Approving plans, specifications, and revised schedule of assessments for the installation of traffic signals at Darwin Road - Packers Avenue Traffic Signal Assessment District. (12th AD)
Body
WHEREAS, the Common Council of the City of Madison adopted the plans, specifications, and schedule of assessment (Leg. File 41797). After approval, certain costs were found to not be included in the calculation of the cost of the project; and
WHEREAS, the assessable funds required to pay for this project were included in Traffic Engineering’s 2017 Capital budget by amending its budget (Leg. File 46372); and
WHEREAS, the Common Council of the City of Madison previously adopted resolutions, declaring its intention to exercise police powers and special assess costs for installation of traffic signals at Darwin Road and Packers Avenue and all other statutory requirements, pursuant to Section 66.0703(4), Wis. Statutes; and
WHEREAS, the Board of Public Works having reported on all the proceedings in relation to the installation of traffic signals at Darwin Road and Packers Avenue in accordance with Section 66.0701 of the Wisconsin Statutes and having in all things duly conformed to the order of the Common Council in relation thereto, and the provisions of the Madison General Ordinances and the Wisconsin Statutes in such case made and provided, and the Common Council being fully advised;
NOW, THEREFORE, BE IT RESOLVED:
1. Traffic Engineering’s 2017 Capital Budget has been increased by $54,578.70 for the assessable portion of the Darwin Road - Packers Avenue Traffic Signal.
2. That traffic signals shall b...
Click here for full text