Fiscal Note
Private Contract. No City Appropriation Required.
Title
Accepting storm sewer and street improvements (including bituminous surface pavement) constructed by Private Contract High Crossing Fifth Addition - Phase 5, and Rescinding RES-18-00323 (17th AD)
Body
WHEREAS, the IA City View, LLC, has satisfactorily completed the installation of storm sewer and street improvements (including bituminous surface pavement) by private contract, in accordance with the City of Madison Standard Specifications for Public Works Construction, in: High Crossing Fifth Addition - Phase 5; and,
WHEREAS, the storm sewer and street improvements (including bituminous surface pavement) were accepted on May 7, 2018 by Resolution RES-18-00323, File Number 51147; and,
WHEREAS, the contract number was incorrect on May 7, 2018 by Resolution RES-18-00323, File Number 51147; and,
WHEREAS, the correct contract number for High Crossing Fifth Addition - Phase 5 is Private Contract Number 7888.
NOW, THEREFORE, BE IT RESOLVED
1. That said storm sewer and street improvements (including bituminous surface pavement) be and are hereby accepted.
2. That said storm sewer improvements are hereby assigned to the Madison Storm Water Utility for ownership and maintenance and that the attached Schedule "A" representing the actual cost of construction of these improvements shall be reflected in the Madison Storm Water Utility's "Utility Plant In Service".
Increase in Total Plant Value per Schedule “A” $111,492.65.
4. That the street improvements, including the bituminous pavement, on the following streets be and are hereby accepted:
· Crossroads Drive from City View Drive to north property line of Lot 3 (CSM 14540)
· City View Drive from 85’ south of Crossroads Drive to 250’ north of Crossroads Drive.
The attached Schedule "A" representing the actual cost of construction of these improvements, which shall increase the street infrastructure value for Project No. 11630 $185,030.92 ...
Click here for full text