Madison, WI Header
File #: 50935    Version: Name: Approving Plans, Specifications and Schedule of Assessments for Winnebago Street, Atwood Avenue and Linden Avenue Assessment District - 2018. (6th AD)
Type: Resolution Status: Vetoed
File created: 3/14/2018 In control: BOARD OF PUBLIC WORKS
On agenda: 5/1/2018 Final action: 5/15/2018
Enactment date: Enactment #: RES-18-00358
Title: Approving Plans, Specifications and Schedule of Assessments for Winnebago Street, Atwood Avenue and Linden Avenue Assessment District - 2018. (6th AD)
Sponsors: Marsha A. Rummel
Attachments: 1. Leg 50935 - Version 1.pdf, 2. Opt1-CrossSection.pdf, 3. Opt2-CrossSection.pdf, 4. Parking Study.PDF, 5. Winnebago_Option 1 - 46ft Plan.pdf, 6. Winnebago_Opt2_Buffered_BikeLane.pdf, 7. FILE 50935 correspondence.pdf, 8. File #50935 Emailed comments 3.2018.pdf, 9. File 50935 Registrant Comments PBMVC 3.27.2018.pdf, 10. Winnebago BPW.pdf, 11. Opt1_Trees.pdf, 12. Opt1A_ExtendBumpouts_Trees.pdf, 13. Opt2_ApproxTrees.pdf, 14. Winnebago BPW Notes.pdf, 15. WinnebagoEmailSubmissions.pdf, 16. 11186_Winnebago-Linden Assess.pdf, 17. PBMVC 3.27.18 ITEM F.3..pdf, 18. Winnebago_AddlEmails.pdf, 19. Fw_ Winnebago St Project.pdf, 20. 50935 Petition.pdf, 21. BPW Hearing Notice June 20 2018.pdf, 22. 50935.pdf
Related files: 52086
Fiscal Note
The proposed resolution approves plan documents for the Winnebago Street contruction project in 2018 at a total estimated cost of $3,285,000. The adopted 2018 capital budget for Engineering Major Streets includes funding for this project within the Reconstruction Streets capital program (MUNIS 11186). The estimated cost of the project is estimated to be distributed between the Engineering division and associated utilities as follows:

Major Streets: $1,305,000
Sewer Utility: $1,100,000
Stormwater Utility: $230,000
Water Utility: $650,000

Title
Approving Plans, Specifications and Schedule of Assessments for Winnebago Street, Atwood Avenue and Linden Avenue Assessment District - 2018. (6th AD)

Body
The Board of Public Works and the City Engineer having made reports of all proceedings in relation to the improvement of Winnebago Street, Atwood Avenue and Linden Avenue Assessment District - 2018 pursuant to a resolution of the Common Council, RES-18-00105, ID No. 50074, adopted February 6, 2018, which resolution was adopted thereto, and the provisions of the Madison General Ordinances and the Wisconsin Statutes in such case made and provided, and the Common Council being fully advised.

BE IT RESOLVED:
1. That the City at large is justly chargeable with and shall pay the sum of $2,827,888 of the entire cost of said improvement.
2. That for those eligible property owners requesting construction of a rain garden in the public right-of-way adjacent to their property shall execute the necessary waiver of special assessments on forms provided by the City Engineer;
3. That the sum assigned to each separate parcel, as indicated on the attached schedule of assessment, is hereby specially assessed upon each such parcel.
4. That the Common Council determines such special assessments to be reasonable.
5. That the work or improvement be carried out in accordance with the reports as finally approved.
6. That such work or improvement represents an exercise of...