Madison, WI Header
File #: 38442    Version: 1 Name: Authorizing the Mayor and City Clerk to enter into an amended purchase of service (Architect) agreement with Meyer Scherer & Rockcastle, Ltd. for $500,000; an agreement with Sustainable Engineering Group LLC for $14,000; and an agreement with Middleton Co
Type: Resolution Status: Passed
File created: 5/12/2015 In control: BOARD OF ESTIMATES (ended 4/2017)
On agenda: 6/16/2015 Final action: 6/16/2015
Enactment date: 6/19/2015 Enactment #: RES-15-00520
Title: Authorizing the Mayor and City Clerk to enter into an amended purchase of service (Architect) agreement with Meyer Scherer & Rockcastle, Ltd. for $500,000 to provide professional architectural and engineering design services; an agreement with Sustainable Engineering Group LLC for $14,000 to provide energy modeling and enhanced commissioning services; and an agreement with Middleton Construction Consulting LLC for $18,000 to provide construction estimating services for the complete rehabilitation of the Madison Municipal Building (MMB).
Sponsors: Paul R. Soglin, Michael E. Verveer, Marsha A. Rummel, Ledell Zellers
Attachments: 1. MMB attachments.pdf
Fiscal Note
Funds are available in the 2015 Capital Budget.
10129-401-140: 54668 (91815)     $500,000
10129-401-140: 54660 (91841)     $14,000
10129-401-140: 54645 (91831)     $18,000
Total estimated cost is $532,000
 
Title
Authorizing the Mayor and City Clerk to enter into an amended purchase of service (Architect) agreement with Meyer Scherer & Rockcastle, Ltd. for $500,000 to provide professional architectural and engineering design services; an agreement with Sustainable Engineering Group LLC for $14,000 to provide energy modeling and enhanced commissioning services; and an agreement with Middleton Construction Consulting LLC for $18,000 to provide construction estimating services for the complete rehabilitation of the Madison Municipal Building (MMB).
 
Body
Preamble
 
The parties, the City of Madison ("City") and Meyer Scherer & Rockcastle, Ltd. ("Architect" or "Contractor") entered into a contract for the purchase of professional architectural pre-design (programming and preliminary concept) services for the MMB and City-County Building (CCB) on July 15, 2014 (RES-14-00545); and a contract amendment to study three design and cost scenarios at MMB on January 6, 2015 (RES-15-00027).  The contract amendment for this resolution is to proceed with - and complete - the schematic design process to pursue a full rehabilitation of the MMB.  Through intensive design engagement with City staff, internal/external stakeholder groups, City leadership, and elected officials the intended outcome of schematic design will include a set of architectural and engineering documents, drawings, narratives, renderings, and construction estimates in sufficient detail to communicate a proposed design strategy in alignment with the authorized budget.  The project is targeted LEED 2009/V3 Silver; and as a National Historic Landmark shall be reviewed by the Wisconsin State Historic Preservation Office.  
 
Sustainable Engineering Group, LLC was selected to provide enhanced commissioning and energy modeling for the schematic design phase in compliance with the City Finance's Purchasing Guidelines for a Purchase of Services Contract between $5000-$25,000.
 
Middleton Construction Consulting, LLC was selected to provide estimating services for the schematic design phase in compliance with the City Finance's Purchasing Guidelines for a Purchase of Services Contract between $5000-$25,000.
 
NOW, THEREFORE BE IT RESOLVED that City staff and the consultant team are hereby authorized to proceed with the schematic design phase for a full rehabilitation of the MMB, and
 
BE IT FURTHER RESOLVED that the Mayor and City Clerk are herby authorized to execute an amendment to the current contract between the City of Madison and Meyer Scherer & Rockcastle, Ltd., in a form to be approved by the City Attorney, to provide professional architectural and engineering design services for the extra work as described above; and execute an agreement with Sustainable Engineering Group, LLC to provide enhanced commissioning and energy modeling services ; and execute an agreement with Middleton Construction Consulting, LLC  to provide estimating services for the schematic design phase.