Title: Approving plans and specifications and authorizing the Mayor and City Clerk to enter into agreements with the Wisconsin Department of Transportation for the construction of East Washington Avenue Segment Four (STH 30 Interchange). (15th & 17th ADs)
Sponsors: Joseph R. Clausius, Larry Palm
Fiscal Note
Breakdown of Total Project Cost

Total Cost $16,500,000
City Cost $ 2,400,000
Federal STP Urban $ 6,400,000
Other State/Federal $ 7,700,000

Breakdown of City Cost

Total City Cost $ 2,400,000
Street Fund $ 1,300,000 CS53-58250-810370-00-53B0204
Sanitary Sewer $ 300,000 ES01-58275-810330-00-53B0204
Water Main $ 800,000 Water Utility Fund

The Comptroller shall encumber $1,025,000 for the anticipated shortage of STP Urban Funds. The agreement requires the City to pay all costs in excess of available State and Federal Funds and a shortage is anticipated. The City share shown above includes the anticipated shortage in funds.

Funds for this project shall be included in the 2009 Capital Budget

Title
Approving plans and specifications and authorizing the Mayor and City Clerk to enter into agreements with the Wisconsin Department of Transportation for the construction of East Washington Avenue Segment Four (STH 30 Interchange). (15th & 17th ADs)
Body

PREAMBLE

The City of Madison and the Wisconsin Department of Transportation have prepared the plans for the reconstruction of East Washington Avenue Segment Four. The reconstruction of East Washington Avenue Segment Four includes reconstructing East Washington Avenue from Marquette Street to Pinecrest Drive, reconstructing Aberg Avenue/ STH 30 from McCormick Ave to Fair Oaks Ave, a cul-de-sac on McCormick Avenue, on and off ramps at Hwy 30 to provide for all traffic movements at the intersection, Fair Oaks Avenue STH 30 on and off ramps, and Fair Oaks Avenue at STH 30.

The project also includes replacement of the sanitary sewer, storm sewer and water main as needed, street lighting, and a new East Washington Avenue Bridge over STH 30 including aesthetic treatments. Bike lanes will be provided on East Washington Avenue.

The project will be funded with State and Federal Funds and those funds will cover a significant portion of the cost of reconstruction. The State of Wiscon...