Madison, WI Header
File #: 55298    Version: 1 Name: Approving Plans, Specifications, And Schedule Of Assessments For South Point Road Assessment District - 2019.
Type: Resolution Status: Passed
File created: 4/4/2019 In control: BOARD OF PUBLIC WORKS
On agenda: 4/30/2019 Final action: 4/30/2019
Enactment date: 5/6/2019 Enactment #: RES-19-00333
Title: Approving Plans, Specifications, And Schedule Of Assessments For South Point Road Assessment District - 2019. (9th AD)
Sponsors: BOARD OF PUBLIC WORKS
Attachments: 1. BPW Hearing South Point Road.pdf, 2. South Point Rd Overview.pdf, 3. South Point Rd Typical Section.pdf, 4. 11871_South Point Assess.pdf, 5. Adoped Mailing CC Leg 55298.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsWatch
4/30/20191 COMMON COUNCIL Adopt Under Suspension of Rules 2.04, 2.05, 2.24, and 2.25, and Close the Public HearingPass Action details Meeting details Not available
4/17/20191 BOARD OF PUBLIC WORKS RECOMMEND TO COUNCIL TO ADOPT UNDER SUSPENSION OF RULES 2.04, 2.05, 2.24 & 2.25 - PUBLIC HEARINGPass Action details Meeting details Not available
4/9/20191 Engineering Division Refer  Action details Meeting details Not available
Fiscal Note
The proposed resolution approves plan documents for the south point road construction project at total estimated cost of $1,286,300. Funding for the project is provided by GO Borrowing and associated utility components within the adopted 2019 Engineering Major Streets capital budget via the Reconstruction Streets capital program.

MUNIS:

11871-402-170 STREET $745,000
11871-402-174 STREET-STORM $69,000
11871-84-174 STORM $347,300
11871-83-173 SEWER $10,000
11871-402-177 STREET LIGHTS $115,000


Title
Approving Plans, Specifications, And Schedule Of Assessments For South Point Road Assessment District - 2019. (9th AD)
Body
The Board of Public Works and the City Engineer having made reports of all proceedings in relation to the improvement of South Point Road Assessment District - 2019 pursuant to a resolution of the Common Council, RES No. 19-00233, ID No. 54980, adopted 03/19/2019, which resolution was adopted thereto, and the provisions of the Madison General Ordinances and the Wisconsin Statutes in such case made and provided, and the Common Council being fully advised.

BE IT RESOLVED:
1. That the City at large is justly chargeable with and shall pay the sum of
$1,286,300.00 of the entire cost of said improvement.
2. That for those eligible property owners requesting construction of a rain garden in the public right-of-way adjacent to their property shall execute the necessary waiver of special assessments on forms provided by the City Engineer;
3. That the sum assigned to each separate parcel, as indicated on the attached schedule of assessment, is hereby specially assessed upon each such parcel.
4. That the Common Council determines such special assessments to be reasonable.
5. That the work or improvement be carried out in accordance with the reports as finally approved.
6. That such work or improvement represents an exercise of...

Click here for full text