Fiscal Note
Funds are available in Acct. No.
Total Cost $2,295,200
Assessable $168,118
City Share $2,127,082
Street 10258-402-170 $655,000
Street/Storm 10258-402-174 $120,000
San. Sewer 10258-83-173 $497,000
Storm 10258-84-174 $379,000
Storm-rain gardens 10258-84-174-84100 $16,200
Storm-catchbasins 10258-84-174-84500 $13,000
Water 10258-86-130 $615,000
Title
Approving Plans, Specifications, And Schedule Of Assessments For Adams Street, Randall Avenue and Mound Street Resurfacing Assessment District - 2015.
Body
The Board of Public Works and the City Engineer having made reports of all proceedings in relation to the improvement of Adams Street, Randall Avenue and Mound Street Resurfacing Assessment District - 2015 pursuant to a resolution of the Common Council, RES-15-00011, ID No. 36274, adopted 1/6/2015, which resolution was adopted thereto, and the provisions of the Madison General Ordinances and the Wisconsin Statutes in such case made and provided, and the Common Council being fully advised.
BE IT RESOLVED:
1. That the City at large is justly chargeable with and shall pay the sum of $2,127,082.00 of the entire cost of said improvement.
2. That for those eligible property owners requesting construction of a rain garden in the public right-of-way adjacent to their property shall execute the necessary waiver of special assessments on forms provided by the City Engineer;
3. That the sum assigned to each separate parcel, as indicated on the attached schedule of assessment, is hereby specially assessed upon each such parcel.
4. That the Common Council determines such special assessments to be reasonable.
5. That the work or improvement be carried out in accordance with the report...