File #: 66469    Version: 1 Name: Assessing Benefits - Cottage Grove Road Reconstruction Assessment District - 2020.
Type: Resolution Status: Passed
File created: 7/14/2021 In control: Engineering Division
On agenda: 8/3/2021 Final action: 8/3/2021
Enactment date: 8/6/2021 Enactment #: RES-21-00539
Title: Assessing Benefits - Cottage Grove Road Reconstruction Assessment District - 2020. (3rd & 16th ADs)
Sponsors: BOARD OF PUBLIC WORKS
Attachments: 1. 53W0472 Final Cottage Grove Road Assess.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsWatch
8/3/20211 COMMON COUNCIL Adopt Under Suspension of Rules 2.04, 2.05, 2.24, and 2.25Pass Action details Meeting details Not available
7/21/20211 BOARD OF PUBLIC WORKS RECOMMEND TO COUNCIL TO ADOPT UNDER SUSPENSION OF RULES 2.04, 2.05, 2.24, & 2.25 - REPORT OF OFFICERPass Action details Meeting details Not available
7/14/20211 Engineering Division Refer  Action details Meeting details Not available

Fiscal Note

No City appropriation required.

Title

Assessing Benefits - Cottage Grove Road Reconstruction Assessment District - 2020. (3rd & 16th ADs)

Body

WHEREAS, the construction of improvement(s) on Cottage Grove Road Reconstruction Assessment District - 2020 has been completed; and,

 

WHEREAS, it has been determined that the abutting property is to pay the amount per the attached schedule of assessments.

 

NOW, THEREFORE, BE IT RESOLVED, that the sums so charged to the abutting property be and are hereby assessed and levied upon said property payable by the owners of the lots or parcels of land benefited as determined by the Board of Public Works, and in accordance with its recommendations, the amount so charged to each of the lots or parcels of land so benefited being as follows, to wit: