Madison, WI Header
File #: 58544    Version: 1 Name: Accepting sanitary sewer, storm sewer, and street improvements (including bituminous surface pavement) constructed by Private Contract at 2901 University Ave. Private Contract No. 8147.
Type: Resolution Status: Passed
File created: 12/3/2019 In control: Engineering Division
On agenda: 1/7/2020 Final action: 1/7/2020
Enactment date: 1/10/2020 Enactment #: RES-20-00015
Title: Accepting sanitary sewer, storm sewer, and street improvements (including bituminous surface pavement) constructed by Private Contract at 2901 University Ave., Private Contract No. 8147. (5th AD)
Sponsors: BOARD OF PUBLIC WORKS
Attachments: 1. 8147 Storm Schedule A.pdf, 2. 8147 Street Schedule A.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsWatch
1/7/20201 COMMON COUNCIL Adopt Under Suspension of Rules 2.04, 2.05, 2.24, and 2.25Pass Action details Meeting details Not available
12/11/20191 BOARD OF PUBLIC WORKS RECOMMEND TO COUNCIL TO ADOPT UNDER SUSPENSION OF RULES 2.04, 2.05, 2.24, & 2.25 - REPORT OF OFFICERPass Action details Meeting details Not available
12/3/20191 Engineering Division Refer  Action details Meeting details Not available

Fiscal Note

Private Contract. No appropriation required.

Title

Accepting sanitary sewer, storm sewer, and street improvements (including bituminous surface pavement) constructed by Private Contract at 2901 University Ave., Private Contract No. 8147. (5th AD)

Body

WHEREAS, the Flad Development and Investment Corp., has satisfactorily completed the installation of storm sewer and street improvements (including bituminous surface pavement) by private contract, in accordance with the City of Madison Standard Specifications for Public Works Construction, at 2901 University Ave.

 

 

NOW, THEREFORE, BE IT RESOLVED

 

1.  That said storm sewer and street improvements (including bituminous surface pavement) be and are hereby accepted. 

 

2. That said sanitary sewer improvements are hereby assigned to the Madison Sewer Utility for ownership and maintenance and that the attached Schedule "A" representing the actual cost of construction of these improvements shall be reflected in the Madison Sewer Utility's "Utility Plant In Service". 

 

SANITARY SEWER ACCOUNTING DATA

 

A)                     Total Contract Value (including Engineering

                     and Miscellaneous Costs)                                                               $                     0                     

 

B)                     Contributions in Aid of Construction:

                     a)                     Public Sewer Components                                          $                     0                     

                     b)                     Sewer Laterals                                                               $                     0                     

 

C)                     Investments in Capital (MSU Share)                     $                     0                     

 

D)                     Total Plant Value                                                                                    $                     0                     

 

3. That said storm sewer improvements are hereby assigned to the Madison Storm Water Utility for ownership and maintenance and that the attached Schedule "A" representing the actual cost of construction of these improvements shall be reflected in the Madison Storm Water Utility's "Utility Plant In Service". 

 

 

Increase in Total Plant Value per Schedule “A”                     $26,251.50

 

 

4. That the street improvements, including the bituminous pavement, on the following streets be and are hereby accepted:

 

 

                     Ridge St from University Ave to Harvey St

                     Harvey St from 210’ West of Ridge St to Ridge St

 

 

 

The attached Schedule "A" representing the actual cost of construction of these improvements, which shall increase the street infrastructure value for Project No. 11913  $ 24,242.00 for a useful life of 40 years.