Title
Approving temporary construction work with associated noise impacts between the hours of 7:00 PM to 7:00 AM (7:00 PM to 10:00 AM on Sunday) on Old Sauk Rd. (District 9)
Body
The City of Madison Board of Public Works will hold a public hearing on the issue of allowing construction activities, with associated noise impacts, outside the period of 7:00 AM to 7:00 PM (10:00 AM to 7:00 PM on Sunday) for asphalt paving on the following streets:
STREET LIMIT LIMIT
OLD SAUK RD EXCELSIOR DR BELTLINE HWY
Madison General Ordinance section 24.08(3) provides the Common Council the ability to allow construction activities outside of the hours of 7:00 AM to 7:00 PM (10:00 AM to 7:00 PM on Sunday) with the passage of a resolution and a hearing before the Board of Public Works.
The street listed above is scheduled for resurfacing in 2024. The first two phases include replacing deteriorated sections of curb and gutter and removing/milling the pavement. Phases one and two will be completed between 7:00 AM to 7:00 PM. Phases one and two can be performed around normal traffic volumes without adversely affecting the quality of the construction and without a big impact on traffic and business access.
The third phase includes placing the asphalt pavement. The work will take place on one or at most two nights. Phase three may be completed between 7:00 PM to 7:00 AM (7:00 PM to 10:00 AM on Sunday) for the following reasons:
1. Traffic turning in and out of the businesses and at the Beltline Hwy could adversely affect the newly placed asphalt pavement.
2. Access interruptions to businesses and the Beltline Hwy is greatly reduced.
3. Performing this work at a time when traffic volumes are reduced will produce a better product.
4. Safety
NOW THEREFORE BE IT RESOLVED, that construction work, with associated noise impacts, between the hours of 7:00 PM to 7:00 AM (7:00 PM to 10:00 AM on Sunday) on Old Sauk Rd are hereby approved in a...