File #: 62429    Version: 1 Name: Authorizing an amendment to the purchase of services contract with Mead and Hunt for professional architectural and engineering services to include design work associated with re-bidding the Metro Transit Phase 2 Facility Improvement project at the Metro
Type: Resolution Status: Passed
File created: 9/30/2020 In control: Engineering Division
On agenda: 10/20/2020 Final action: 10/20/2020
Enactment date: 10/26/2020 Enactment #: RES-20-00727
Title: Authorizing an amendment to the purchase of services contract with Mead and Hunt for professional architectural and engineering services to include design work associated with re-bidding the Metro Transit Phase 2 Facility Improvement project at the Metro Transit Bus Maintenance Facility. (6th AD)
Sponsors: BOARD OF PUBLIC WORKS
Attachments: 1. 200901_Madison Metro Transit Add Services HVAC_Revised Rebid proposal-MH-signed.pdf
Fiscal Note
The proposed resolution amends a purchase of services contract with Mead and Hunt for design work associated with the Phase 2 HVAC Upgrade at the Metro Transit Bus Maintenance Facility located at 1101 E. Washington Ave. The cost for this amendment is $14,077 and is budgeted within the adopted 2020 capital budget in Metro’s Facilities Repairs and Improvements capital program. In 2020, $8.4 million of GO Borrowing is budgeted for the facility improvements. Mead and Hunt’s current contract totals $1,144,381 for Phase 1 and Phase 2 design and construction administration services.
Title
Authorizing an amendment to the purchase of services contract with Mead and Hunt for professional architectural and engineering services to include design work associated with re-bidding the Metro Transit Phase 2 Facility Improvement project at the Metro Transit Bus Maintenance Facility. (6th AD)
Body
WHEREAS the 2020 Capital Budget includes $8,440,000 for Metro Transit Facilities Repairs and Improvement;

WHEREAS When the Metro Transit Phase 2 was first bid, we received a bid from only one qualified bidder and decided not to open or award it.

WHEREAS Additional design work was required, as outlined in the attached document, to prepare the documents for a rebid.

WHEREAS Mead & Hunt, after a competitive request for proposal (RFP) process, was awarded and completed a building master plan study for the 1101 E. Washington Ave Metro Transit Bus Maintenance Facility in March 2018, and is familiar with the project and design requirements; and

WHEREAS, in addition, Mead & Hunt completed the design work associated with phase 1 of the building master plan study in 2018 which was awarded via an non-competitive purchase of services contract in early 2018 (see File # 50922 ); and

WHEREAS, in addition, Mead & Hunt completed the design work...