Madison, WI Header
File #: 60026    Version: 1 Name: Accepting sanitary sewer, storm sewer, and street improvements constructed by Private Contract In Village at Autumn Lake - Phase 8, Private Contract No. 8237
Type: Resolution Status: Passed
File created: 3/17/2020 In control: Engineering Division
On agenda: 3/31/2020 Final action: 3/31/2020
Enactment date: 4/3/2020 Enactment #: RES-20-00247
Title: Accepting sanitary sewer, storm sewer, and street improvements constructed by Private Contract In Village at Autumn Lake - Phase 8, Private Contract No. 8237 (17th AD)
Sponsors: BOARD OF PUBLIC WORKS
Attachments: 1. 8237_Street Schedule A complete Schedule A.pdf, 2. 8237 Sanitary Schedule A Unit Cost.pdf, 3. 8237 Storm Schedule A Unit Cost.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsWatch
3/31/20201 COMMON COUNCIL Adopt Under Suspension of Rules 2.04, 2.05, 2.24, and 2.25Pass Action details Meeting details Not available
3/25/20201 BOARD OF PUBLIC WORKS RECOMMEND TO COUNCIL TO ADOPT UNDER SUSPENSION OF RULES 2.04, 2.05, 2.24, & 2.25 - REPORT OF OFFICERPass Action details Meeting details Not available
3/17/20201 Engineering Division Refer  Action details Meeting details Not available
Fiscal Note
Private Contract, No City Funds Are Required.
Title
Accepting sanitary sewer, storm sewer, and street improvements constructed by Private Contract In Village at Autumn Lake - Phase 8, Private Contract No. 8237 (17th AD)
Body
WHEREAS, the VAL, LLC, has satisfactorily completed the installation of sanitary sewer, storm sewer, and street improvements by private contract, in accordance with the City of Madison Standard Specifications for Public Works Construction, in: Village at Autumn Lake - Phase 8.


NOW, THEREFORE, BE IT RESOLVED

1. That said sanitary sewer, storm sewer, and street improvements (including bituminous surface pavement) be and are hereby accepted.

2. That said sanitary sewer improvements are hereby assigned to the Madison Sewer Utility for ownership and maintenance and that the attached Schedule "A" representing the actual cost of construction of these improvements shall be reflected in the Madison Sewer Utility's "Utility Plant In Service".

SANITARY SEWER ACCOUNTING DATA

A) Total Contract Value (including Engineering
and Miscellaneous Costs) $ 45,701.87

B) Contributions in Aid of Construction:
a) Public Sewer Components $ 45,701.87
b) Sewer Laterals $ -0-

C) Investments in Capital (MSU Share) $ -0-

D) Total Plant Value $ 45,701.87

3. That said storm sewer improvements are hereby assigned to the Madison Storm Water Utility for ownership and maintenance and that the attached Schedule "A" representing the actual cost of construction of these improvements shall be reflected in the Madison Storm Water Utility's "Utility Plant In Service".


Increase in Total Plant Value per Schedule “A” $60,052.30.


4. That the street improvements on the following streets be and are hereby accepted:


· Lien Road from E Line of Lot 1098 to W Line of Lot 1100
· Lien Road from 134’ W of Felland Road to Felland Road
· Felland Road from Lien Road to 156’ N of Lien Road



The attached Schedule "A" representing the actual c...