Enactment date: 1/10/2020 Enactment #: RES-20-00003
Title: Amending the 2020 Engineering-Major Streets and Engineering-Bicycle and Pedestrian Capital Budgets to transfer $1,300,000 of existing GO borrowing authority between major project Cottage Grove Road and major project Gammon Road, South and West Towne Path Phase 1. (City Wide ADs)
Sponsors: Keith Furman, Paul E. Skidmore
Date Ver.Action ByActionResultAction DetailsMeeting DetailsWatch
1/7/20201 COMMON COUNCIL Adopt Under Suspension of Rules 2.04, 2.05, 2.24 & 2.25 - 15 Votes RequiredPass Action details Meeting details Not available
12/23/20191 Engineering Division RECOMMEND TO COUNCIL TO ADOPT UNDER SUSPENSION OF RULES 2.04, 2.24, & 2.25 - (15 VOTES REQUIRED) - REPORT OF OFFICER  Action details Meeting details Not available
Fiscal Note
The resolution amends the adopted 2020 Engineering-Major Streets and Engineering-Bicycle and Pedestrian Capital Budgets by authorizing a net-neutral transfer of existing budget authority across major projects within the Engineering-Major Streets and Engineering-Bicycle and Pedestrian Capital Budgets. $1.3m of GO borrowing authority will be transferred from the Cottage Grove Road (I39 to Sprecher) project to the Gammon Road project and South and West Towne Path Phase 1 projects. The Cottage Grove Road project as adopted has a 2020 capital budget of $2.87m, including $1.5m in GO Borrowing authority.

($1,300,000) 10230-402-170
($1,300,000) 10230-402-801
$800,000 11130-402-170
$800,000 11130-402-801
$500,000 10168-403-172
$500,000 10168-403-801
Title
Amending the 2020 Engineering-Major Streets and Engineering-Bicycle and Pedestrian Capital Budgets to transfer $1,300,000 of existing GO borrowing authority between major project Cottage Grove Road and major project Gammon Road, South and West Towne Path Phase 1. (City Wide ADs)
Body
WHEREAS, The City of Madison in conjunction with the Wisconsin Department of Transportation (WisDOT) have proposed projects to reconstruct Cottage Grove Road and reconstruct Gammon Road and construct Phase 1 West Towne Path; and

WHEREAS, The City of Madison Common Council adopted RES-19-00644 approving the plans and specifications for the reconstruction of Cottage Grove Road and adopted RES-19-00591 approving the plans and specifications for the reconstruction of Gammon Road and construction of Phase 1 of the West Towne Path, and

WHEREAS, The WisDOT has advertised and received bids for the Cottage Grove Road and Gammon Road and West Towne Path projects, and

WHEREAS, Based on the Bids received, the Gammon Road and West Towne Path project is short of funds in part due to the extensive work and traffic control required to construct the proposed underpass of Gammon Road for the West Towne...