Madison, WI Header
File #: 58647    Version: 1 Name: Accepting sanitary sewer, storm sewer, and street improvements (including bituminous surface pavement) constructed by Private Contract Grandview Commons Phase 21, Private Contract No. 2417.
Type: Resolution Status: Passed
File created: 12/9/2019 In control: Engineering Division
On agenda: 1/7/2020 Final action: 1/7/2020
Enactment date: 1/10/2020 Enactment #: RES-20-00016
Title: Accepting sanitary sewer, storm sewer, and street improvements (including bituminous surface pavement) constructed by Private Contract Grandview Commons Phase 21, Private Contract No. 2417. (3rd AD)
Sponsors: BOARD OF PUBLIC WORKS
Attachments: 1. 2417 Street Schedule A complete Schedule A.pdf, 2. 2417_Grandview Commons Ph 21 Sanitary Schedule A.pdf, 3. 2417_Grandview Commons Ph 21 Storm Schedule A.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsWatch
1/7/20201 COMMON COUNCIL Adopt Under Suspension of Rules 2.04, 2.05, 2.24, and 2.25Pass Action details Meeting details Not available
12/11/20191 BOARD OF PUBLIC WORKS RECOMMEND TO COUNCIL TO ADOPT UNDER SUSPENSION OF RULES 2.04, 2.05, 2.24, & 2.25 - REPORT OF OFFICERPass Action details Meeting details Not available
12/9/20191 Engineering Division Refer  Action details Meeting details Not available
Fiscal Note
Private contract. No appropriation required.
Title
Accepting sanitary sewer, storm sewer, and street improvements (including bituminous surface pavement) constructed by Private Contract Grandview Commons Phase 21, Private Contract No. 2417. (3rd AD)
Body
WHEREAS, the MREC VH Madison, LLC, has satisfactorily completed the installation of sanitary sewer, storm sewer, and street improvements (including bituminous surface pavement) by private contract, in accordance with the City of Madison Standard Specifications for Public Works Construction, in: Grandview Commons Phase 21.


NOW, THEREFORE, BE IT RESOLVED

1. That said sanitary sewer, storm sewer, and street improvements (including bituminous surface pavement) be and are hereby accepted.

2. That said sanitary sewer improvements are hereby assigned to the Madison Sewer Utility for ownership and maintenance and that the attached Schedule "A" representing the actual cost of construction of these improvements shall be reflected in the Madison Sewer Utility's "Utility Plant In Service".

SANITARY SEWER ACCOUNTING DATA

A) Total Contract Value (including Engineering
and Miscellaneous Costs) $ 21,990.48

B) Contributions in Aid of Construction:
a) Public Sewer Components $ 21,990.48
b) Sewer Laterals $ -0-

C) Investments in Capital (MSU Share) $ -0-

D) Total Plant Value $ 21,990.48



3. That said storm sewer improvements are hereby assigned to the Madison Storm Water Utility for ownership and maintenance and that the attached Schedule "A" representing the actual cost of construction of these improvements shall be reflected in the Madison Storm Water Utility's "Utility Plant In Service".


Increase in Total Plant Value per Schedule “A” $71,416.02.


4. That the street improvements, including the bituminous pavement, on the following streets be and are hereby accepted:


· North Star Drive from the north lot line of Lot 890 to north lot line of Lot 30
· Caldera Street from th...

Click here for full text