File #: 49015    Version: 1 Name: Approving plans and specifications and authorizing the Board of Public Works to advertise and receive bids for the Madison Fire Department Fire Station 14.
Type: Resolution Status: Passed
File created: 9/26/2017 In control: BOARD OF PUBLIC WORKS
On agenda: 10/17/2017 Final action: 10/17/2017
Enactment date: 10/19/2017 Enactment #: RES-17-00833
Title: Approving plans and specifications and authorizing the Board of Public Works to advertise and receive bids for the Madison Fire Department Fire Station 14. (16th AD)
Sponsors: BOARD OF PUBLIC WORKS
Attachments: 1. FS14 BPW Pres.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsWatch
10/17/20171 COMMON COUNCIL Adopt Under Suspension of Rules 2.04, 2.05, 2.24, and 2.25Pass Action details Meeting details Not available
10/4/20171 BOARD OF PUBLIC WORKS RECOMMEND TO COUNCIL TO ADOPT UNDER SUSPENSION OF RULES 2.04, 2.05, 2.24, & 2.25 - REPORT OF OFFICERPass Action details Meeting details Not available
9/26/20171 Engineering Division Refer  Action details Meeting details Not available
Fiscal Note
The proposed resolution authorizes the Board of Public Works to advertise and receive bids for Fire Station 14. The 2017 Fire Department Adopted Capital Budget includes $450,000 for design and the 2018 Fire Department Executive Capital Budget includes $6,300,000 for construction and equipment costs for Station 14 (Munis project 17451). The anticipated construction cost for Station 14 is $6,450,000. The project includes installing solar improvements on the roof at an estimated cost of $150,000 which will be funded by the 2018 Engineering-Facilities Management Executive Capital Budget Sustainability Improvements project (Munis project 10563).
Title
Approving plans and specifications and authorizing the Board of Public Works to advertise and receive bids for the Madison Fire Department Fire Station 14. (16th AD)
Body
WHEREAS the 2017 Capital Improvement Plan includes $450,000 for design and the 2018 Executive Capital Budget - Capital Improvement Plan request includes $6,300,000 for construction of the Fire Station 14 project; and,

WHEREAS the project includes installing solar PV on the roof at an estimated cost of $150,000 which will require a future transfer of budget authority, after the bids are received, from the Sustainability Improvements Major Project in the 2018 Engineering-Facilities Management capital budget.

WHEREAS this resolution approves the plans and specifications for the project, and allows the project to be advertised and receive bids.

NOW, THEREFORE BE IT RESOLVED

1) That the plans and specifications for Fire Station 14, be and are hereby approved.

2) That the Board of Public Works be and is hereby authorized to advertise and receive bids for said project.

3) That the Mayor and City Clerk are hereby authorized to sign and grant easements or right-of-way release or procurement documents, maintenance agreements or encroachment agreements, as necessary and grant or accept dedication of lands and/or easements from/to the Develo...

Click here for full text