File #: 42788    Version: 1 Name: Authorizing the Mayor and the City Clerk to execute a revised agreement with the Wisconsin Department of Transportation for design and construction of the High Point Road Bridge and Approaches over the West Beltline Highway (USH 12/14).
Type: Resolution Status: Passed
File created: 5/3/2016 In control: BOARD OF PUBLIC WORKS
On agenda: 5/17/2016 Final action: 5/17/2016
Enactment date: 5/19/2016 Enactment #: RES-16-00386
Title: Authorizing the Mayor and the City Clerk to execute a revised agreement with the Wisconsin Department of Transportation for design and construction of the High Point Road Bridge and Approaches over the West Beltline Highway (USH 12/14).
Sponsors: BOARD OF PUBLIC WORKS
Date Ver.Action ByActionResultAction DetailsMeeting DetailsWatch
5/17/20161 COMMON COUNCIL Adopt Under Suspension of Rules 2.04, 2.05, 2.24, and 2.25Pass Action details Meeting details Not available
5/4/20161 BOARD OF PUBLIC WORKS RECOMMEND TO COUNCIL TO ADOPT UNDER SUSPENSION OF RULES 2.04, 2.05, 2.24, & 2.25 - REPORT OF OFFICER  Action details Meeting details Not available
5/3/20161 Engineering Division Refer  Action details Meeting details Not available

Fiscal Note

In the adopted 2016 capital budget, Engineering - Major Streets has budgeted for the High Point Road Bridge over the Beltline (MUNIS 10441) in the amount of $1.15 million.  The project will replace the existing bridge with a new four lane bridge. Funding for this project is from GO borrowing.

 

The proposed resolution authorizes the agreement at a cost to the city of $1,492,300.

 

MUNIS:

10441-402-171

 

Title

Authorizing the Mayor and the City Clerk to execute a revised agreement with the Wisconsin Department of Transportation for design and construction of the High Point Road Bridge and Approaches over the West Beltline Highway (USH 12/14).

Body

PREAMBLE

 

The City of Madison and Wisconsin Department of Transportation entered into an agreement authorized by Resolution File ID 19697, RES-10-00816 for the design and construction of the High Point Road Bridge and Approaches over the West Beltline Highway (USH 12/14).

 

The bridge is in very poor condition and requires complete removal and replacement.

 

The bridge reconstruction is funded with both federal (75%) and City (25%) funds.

 

At the City’s request, the design now includes extension of the bridge to allow the West Towne Mutli-use Path to cross the beltline with the bridge.  Additional federal and City funds are required.

 

Construction is scheduled for 2017.  $1,000,000 of budget authority remains in account 10441 as included in the 2016 capital budget, and the remainder will be budgeted for in 2017.

 

BE IT RESOLVED, that the Mayor and City Clerk are hereby authorized to execute a revised agreement with the Wisconsin Department of Transportation for design and construction of the High Point Road Bridge and Approaches over the West Beltline Highway (USH 12/14).