File #: 33605    Version: 1 Name: Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM on W. Beltline Frontage Rd, W. Badger Rd, Wayne Ter, Benjamin Dr. and Deming Way.
Type: Resolution Status: Passed
File created: 4/14/2014 In control: BOARD OF PUBLIC WORKS
On agenda: 4/29/2014 Final action: 4/29/2014
Enactment date: 4/30/2014 Enactment #: RES-14-00331
Title: Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM on W. Beltline Frontage Rd, W. Badger Rd, Wayne Ter, Benjamin Dr. and Deming Way.
Sponsors: Joseph R. Clausius, Paul E. Skidmore, John Strasser
Attachments: 1. bpw mailing affidavit.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsWatch
4/29/20141 COMMON COUNCIL Adopt Under Suspension of Rules 2.04, 2.05, 2.24, and 2.25Pass Action details Meeting details Not available
4/23/20141 BOARD OF PUBLIC WORKS RECOMMEND TO COUNCIL TO ADOPT UNDER SUSPENSION OF RULES 2.04, 2.05, 2.24, & 2.25 - REPORT OF OFFICERPass Action details Meeting details Not available
4/18/20141 Engineering Division Refer  Action details Meeting details Not available
Fiscal Note
No funds Required.
Title
Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM on W. Beltline Frontage Rd, W. Badger Rd, Wayne Ter, Benjamin Dr. and Deming Way.
Body
PREAMBLE

The City of Madison Board of Public Works will hold a public hearing on the issue of allowing construction activities, with associated noise impacts, outside the period of 7:00 AM to 7:00 PM for certain work items on the following streets:

W. Beltline Frontage Rd (Whalen R - Damon Rd)
W. Badger Rd (Fish Hatchery Rd - West End)
Wayne Terrace (Lancaster Dr - High Crossing Blvd)
Lancaster Dr (High Crossing Blvd - Wayne Ter)
Benjamin Dr (High Crossing Blvd - Wayne Ter)
Deming Way (Blackhawk Rd - Fourier Dr)

The Public Hearing will be on Wednesday April 23rd, 2014 at 5:30 PM at the City County Building, 210 Martin Luther King Jr. Blvd, Room 108A.

Madison General Ordinance section 24.08(3) provides the Common Council the ability to allow construction activities outside of the hours of 7:00 AM to 7:00 PM. with the passage of a resolution and a hearing before the Board of Public Works.

The streets listed above are scheduled for resurfacing in 2014. The first phase includes replacing deteriorated sections of curb and gutter. The second phase includes pulverizing the pavement. The third phase includes placing the asphalt pavement. Phases one and two will be completed between the hours of 7:00 AM and 7:00 PM. Phase three will be completed between the hours of 7:00 PM and 7:00 AM for the following reasons:

1. Phases one and two can be performed around normal traffic volumes without adversely affecting the quality of the construction and without a big impact on traffic. The contractor is required to maintain access to all businesses at all times.

2. Traffic turning in and out of the businesses could adversely affect the newly placed asphalt pavement in Phase three. Performing this work during reduced traffic volumes w...