Madison, WI Header
File #: 31943    Version: 1 Name: Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM on East Johnson Street from North Butler Street to North Baldwin Street.
Type: Resolution Status: Passed
File created: 10/18/2013 In control: BOARD OF PUBLIC WORKS
On agenda: 11/19/2013 Final action: 11/19/2013
Enactment date: 11/20/2013 Enactment #: RES-13-00853
Title: Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM on East Johnson Street from North Butler Street to North Baldwin Street. (2nd AD)
Sponsors: BOARD OF PUBLIC WORKS
Attachments: 1. Noise Variance-E Johnson St Reconstruction.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsWatch
11/19/20131 COMMON COUNCIL Adopt Under Suspension of Rules 2.04, 2.05, 2.24, and 2.25Pass Action details Meeting details Not available
10/30/20131 BOARD OF PUBLIC WORKS RECOMMEND TO COUNCIL TO ADOPT UNDER SUSPENSION OF RULES 2.04, 2.05, 2.24, & 2.25 - REPORT OF OFFICERPass Action details Meeting details Not available
10/22/20131 Engineering Division Refer  Action details Meeting details Not available
Fiscal Note
No Funds Required.

Title
Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM on East Johnson Street from North Butler Street to North Baldwin Street. (2nd AD)
Body
The City of Madison has proposed a project to reconstruct East Johnson Street from N Butler Street to N Baldwin Street in 2014. The proposed project includes the replacement of sanitary sewer, storm sewer, water main, street lights, traffic signals, curb & gutter and asphalt pavement. Due to the volume of traffic on East Johnson Street, and the expedited work schedule, we propose to allow Contractors to work between the hours of 7:00 PM to 7:00 AM. Work between the hours of 7:00 PM to 7:00 AM will be allowed only on a limited basis when deemed necessary, and must be preapproved by the City Engineer.

Madison General Ordinance section 24.08(3) provides the Common Council the ability to allow construction activities outside of the hours of 7:00 AM to 7:00 PM with the passage of a resolution and a hearing before the Board of Public Works.

The work associated with the project cannot be fully constructed between the hours of 7:00 AM and 7:00 PM because:

1. The amount of construction needed to complete the project exceeds the amount of production that a Contractor can reasonably be expected to achieve between the hours of 7:00 AM and 7:00 PM, even with the extra crews.

2. Private utility companies will be installing infrastructure in conjunction with the project that will require the closure of all travel lanes on East Johnson Street, at limited times, to allow the placement of large concrete utility vaults. When necessary, the closure of all travel lanes will be allowed for short periods of time and will take place during night time, off peak travel hours to limit the impact and delay to the traveling public.


The proposed activities beyond the hours of 7:00 AM to 7:00 PM are as follows:

1) General construction activitie...

Click here for full text