File #: 29581    Version: 1 Name: Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM on Tokay Blvd and Wright St
Type: Resolution Status: Passed
File created: 3/26/2013 In control: BOARD OF PUBLIC WORKS
On agenda: 4/30/2013 Final action: 4/30/2013
Enactment date: 5/3/2013 Enactment #: RES-13-00316
Title: Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM on Tokay Blvd and Wright St.
Sponsors: BOARD OF PUBLIC WORKS
Date Ver.Action ByActionResultAction DetailsMeeting DetailsWatch
4/30/20131 COMMON COUNCIL Adopt Under Suspension of Rules 2.04, 2.05, 2.24, and 2.25Pass Action details Meeting details Not available
4/17/20131 BOARD OF PUBLIC WORKS RECOMMEND TO COUNCIL TO ADOPT UNDER SUSPENSION OF RULES 2.04, 2.05, 2.24, & 2.25 - REPORT OF OFFICERPass Action details Meeting details Not available
3/26/20131 Engineering Division Referred for Introduction  Action details Meeting details Not available
Fiscal Note
No funds Required

Title
Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM on Tokay Blvd and Wright St.

Body

PREAMBLE

Tokay Blvd (Whitney Way - Odana Rd) & Wright St (Kinsman Blvd - Anderson St) is scheduled for resurfacing in 2013. The first phase includes replacing deteriorated sections of curb and gutter. The second phase includes pulverizing the pavement and placing back the lower layer of pavement. The third phase includes placing the final surface of pavement. Phases one and two will be completed between the hours of 7:00 AM and 7:00 PM. Phase three will be completed between the hours of 9:00 PM and 6 AM for the following reasons:

1. Phases one and two can be performed around normal traffic volumes without adversely affecting the quality of the construction and without a big impact on traffic. The contractor is required to maintain access to all businesses at all times. This work will last approximately 2 to 3 weeks.
2. Traffic turning in and out of the businesses could adversely affect the newly placed surface in Phase three. Performing this work during reduced traffic volumes will produce a better product and provide the least interruption to the businesses. This work will take place on two consecutive nights at each location.

The proposed activities beyond the hours of 7:00 AM to 7:00 PM are as follows:

1. Placing the final surface of asphalt pavement on Tokay Blvd & Wright St.

Construction activities generally exceed the noise limits imposed by the Madison General Ordinances and temporary construction activity between the hours of 7:00 AM to 7:00 PM is allowed to exceed the noise limits imposed by the Madison General Ordinances. Madison General Ordinance section 24.08(3) provides the Common Council the ability to allow construction activities, with associated noise impacts, outside of the hours of 7:00 AM to 7:00 PM. with the passage of a resolution.

NOW...

Click here for full text