File #: 28637    Version: 1 Name: Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM on Schroeder Road and Whitney Way.
Type: Resolution Status: Passed
File created: 12/17/2012 In control: BOARD OF PUBLIC WORKS
On agenda: 1/22/2013 Final action: 1/22/2013
Enactment date: 1/23/2013 Enactment #: RES-13-00057
Title: Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM on Schroeder Road and Whitney Way.
Sponsors: Brian L. Solomon, Matthew J. Phair
Fiscal Note
No Funds Required.
Title
Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM on Schroeder Road and Whitney Way.
Body
PREAMBLE
The 2012 Phase 1 contract for cured-in-place rehabilitation includes the lining of approximately 22,990 linear feet of sanitary sewer mains.  The contractor performing this work has requested permission to perform the work required to line one segment of sanitary sewer main in Schroeder Road and Whitney way outside the hours of 7:00 AM to 7:00 PM to begin no earlier than Monday, January 28th, 2013 and complete no later than Friday, February 8th, 2013. The total length of this sanitary sewer main is 270 linear feet.
 
Madison General Ordinance section 24.08(3) provides the Common Council the ability to allow construction activities outside of the hours of 7:00 AM to 7:00 PM with the passage of a resolution and a hearing before the Board of Public Works. The contractor performing this work has requested permission to perform the work required to line the one segment of sanitary sewer main in Schroeder Road and Whitney Way outside the hours of 7:00 AM to 7:00 PM because:
 
1.      The section of sanitary sewer main to be lined has high flow during the hours of 7:00 AM to 7:00 PM.
2.      The streets where this work is scheduled to occur convey high volumes of traffic. Activities associated with lining these sanitary mains will disrupt live traffic causing considerable disruption and delay.  
 
The proposed activities beyond the hours of 7:00 AM to 7:00 PM are as follows:
 
1.      Hydraulic cleaning of the sanitary sewer main sections to be lined to remove any accumulated debris prior to lining;
2.      Conducting a closed-circuit inspection of the sanitary sewer mains to be lined to confirm that the line has been adequately cleaned prior to lining and to provide documentation to the City of pre-lining. conditions;
3.      Installing the resin-impregnated felt liner into the sanitary sewer main;
4.      Using steam to cure the liner in place;
5.      Conducting a closed-circuit inspection of the lined sections of sanitary sewer mains to provide documentation to the City that all required work has been satisfactorily performed.
 
NOW THEREFORE BE IT RESOLVED, that construction work, with associated noise impacts, between the hours of 7:00 PM and 7:00 AM in Schroeder Road and Whitney Way are hereby approved in accordance with Section 24.08(3) of the Madison General Ordinances., and
 
BE IT FURTHER RESOLVED, that the construction activities outside the hours of 7:00 AM and 7:00 PM are limited to those activities identified in this resolution and the hours specified, and
 
BE IT FURTHER RESOLVED, that the approval of that construction work, as provided in this resolution shall expire on February 8th, 2012.