Title
Improvements accepted for Sidewalk and Curb and Gutter, Citywide Installation and Repair - 2010, Contract No. 6421.
Body
BE IT RESOLVED, that the improvements on Sidewalk and Curb and Gutter, Citywide Installation and Repair - 2010 have been completed on 11/17/10 be and are hereby accepted.
Original Contract Sum $ 448,190.00
(Based on Actual Units) $ 207,682.64
Net Change by Change Orders $ 0.00 or 0.00%
Liquidated Damages $ 0.00
Final Contract Amount $ 207,682.64
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-54473-810376-00-53W0881 $166,851.65
Acc't. No. CS53-58280-810376-00-53W0881 $30,803.57
Acc't. No. CS53-54472-810358-00-53W0881 $10,027.42