Madison, WI Header
File #: 21927    Version: 1 Name: Improvements Accepted for water service laterals by private contract to serve: Eastlawn - Phase 1
Type: Resolution Status: Passed
File created: 3/29/2011 In control: BOARD OF PUBLIC WORKS
On agenda: 4/19/2011 Final action: 4/19/2011
Enactment date: 4/27/2011 Enactment #: RES-11-00346
Title: Improvements Accepted for water service laterals by private contract to serve: Eastlawn - Phase 1 (3rd AD)
Sponsors: BOARD OF PUBLIC WORKS

Fiscal Note

No Funds Required.

 

Title

Improvements Accepted for water service laterals by private contract to serve: Eastlawn - Phase 1 (3rd AD)

 

Body

Resolved, that water service lateral installation improvements in Eastlawn - Phase 1, which have been completed, be and are hereby approved, and that the Water Utility General Manager be authorized to accept surety in the amount of $2,500 to expire not earlier than April 19, 2012 to ensure performance of the one-year guaranty period.