Title

Madison Gas and Electric Company (MGE) will replace the gas mains and service laterals on the 3600 block of Busse St and the 3500 block of Margaret St.  This work will be started in August 2010 and completed by mid to late October 2010.

 

Body

A public hearing, for this project, will be held before the City of Madison Board of Public Works at 5:30 p.m. on Wednesday, July 7. 2010 in Room 108 of the City-County Building, 210 Martin Luther King Jr. Blvd.

 

Gas pipes will be replaced in the street terrace and in your yard.  Work will be done by MGE and KS Energy Services in accordance with the City's Tree Care Standards and in compliance with a Permit to Excavate in Public Right-of-Way.

 

The surface restoration will be done upon completion of the gas main replacement.

 

The restoration will be done as required by the Permit to Excavate in Public Right-of Way.  If you have questions or concerns about this project, please call or e-mail Don McClain at (608) 252-5618, dmcclain@mge.com <mailto:dmcclain@mge.com>, or Larry Capps at (608) 252-7224, lcapps@mge.com <mailto:lcapps@mge.com>.  You can also fax us at (608) 252-5658.