File #: 18438    Version: 1 Name: Improvements accepted for Annual Construction & Reconstruction of Concrete Sidewalk & Incidental Concrete Curb & Gutter Work Ordered (District 9) by the Common Council, Contract No. 6296.
Type: Resolution Status: Passed
File created: 5/10/2010 In control: COMMON COUNCIL
On agenda: 6/1/2010 Final action: 6/1/2010
Enactment date: 6/4/2010 Enactment #: RES-10-00518
Title: Improvements accepted for Annual Construction & Reconstruction of Concrete Sidewalk & Incidental Concrete Curb & Gutter Work Ordered (District 9) by the Common Council, Contract No. 6296.
Sponsors: BOARD OF PUBLIC WORKS
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-54473-810376-00-53W0706      $691,141.95
Acc't. No. CS53-58280-810376-00-53W0706          $1,850.41.
Title
Improvements accepted for Annual Construction & Reconstruction of Concrete Sidewalk & Incidental Concrete Curb & Gutter Work Ordered (District 9) by the Common Council, Contract No. 6296.
Body
BE IT RESOLVED, that the improvements on Annual Construction & Reconstruction of Concrete Sidewalk & Incidental Concrete Curb & Gutter Work Ordered (District 9) by the Common Council have been completed on 8/19/09 be and are hereby accepted.  
 
Original Contract Sum      $         697,485.00
(Based on Actual Units)      $         692,992.36
Net Change by Change Orders      $                  0.00 or 0.00%
Liquidated Damages      $                  0.00
Final Contract Amount      $        692,992.36.