Madison, WI Header
File #: 17272    Version: 1 Name: Accepting sanitary sewer, storm sewer, and street improvements (excluding bituminous surface pavement) constructed by Private Contract In Grandview Commons Phase 15A, Private Contract No. 2085.
Type: Resolution Status: Passed
File created: 1/26/2010 In control: BOARD OF PUBLIC WORKS
On agenda: 2/23/2010 Final action: 2/23/2010
Enactment date: 2/26/2010 Enactment #: RES-10-00160
Title: Accepting sanitary sewer, storm sewer, and street improvements (excluding bituminous surface pavement) constructed by Private Contract In Grandview Commons Phase 15A, Private Contract No. 2085. (3rd AD)
Sponsors: BOARD OF PUBLIC WORKS
Attachments: 1. 2085.pdf
Title
Accepting sanitary sewer, storm sewer, and street improvements (excluding bituminous surface pavement) constructed by Private Contract In Grandview Commons Phase 15A, Private Contract No. 2085. (3rd AD)
Body

WHEREAS, Premium Real Estate, LLC has satisfactorily completed the installation of sanitary sewer, storm sewer, and street improvements (excluding bituminous surface pavement) by private contract, in accordance with the City of Madison Standard Specifications for Public Works Construction, in: Grandview Commons Phase 15A


NOW, THEREFORE, BE IT RESOLVED

1. That said sanitary sewer, storm sewer, and street improvements (excluding bituminous surface pavement) be and are hereby accepted.

2. That said sanitary sewer improvements are hereby assigned to the Madison Sewer Utility for ownership and maintenance and that the attached Schedule "A" representing the actual cost of construction of these improvements shall be reflected in the Madison Sewer Utility's "Utility Plant In Service".

SANITARY SEWER ACCOUNTING DATA

A) Total Contract Value (including Engineering
and Miscellaneous Costs) $ 17,080.14

B) Contributions in Aid of Construction:
a) Public Sewer Components $ 17,080.14
b) Sewer Laterals $ -0-_

C) Investments in Capital (MSU Share) $ -0-

D) Total Plant Value $ 17,080.14

3. That said storm sewer improvements are hereby assigned to the Madison Storm Water Utility for ownership and maintenance and that the attached Schedule "A" representing the actual cost of construction of these improvements shall be reflected in the Madison Storm Water Utility's "Utility Plant In Service".


Increase in Total Plant Value per Schedule “A” $ 278,144.35

4. That the street improvements, excluding the bituminous pavement, on the following streets be and are hereby accepted:

· North Star Drive from the northerly line of Lot 166 (existing street) to the southerly line of Lot 153.
· Dominion Drive from North Star Drive to the east line o...

Click here for full text