File #: 16816    Version: 1 Name: Improvements accepted for Sayle Street Traffic Engineering Warehouse Building Phase 2 Building Construction, Contract No. 6218.
Type: Resolution Status: Passed
File created: 12/4/2009 In control: BOARD OF PUBLIC WORKS
On agenda: 1/5/2010 Final action: 1/5/2010
Enactment date: 1/6/2010 Enactment #: RES-10-00025
Title: Improvements accepted for Sayle Street Traffic Engineering Warehouse Building Phase 2 Building Construction, Contract No. 6218.
Sponsors: BOARD OF PUBLIC WORKS
Title
Improvements accepted for Sayle Street Traffic Engineering Warehouse Building Phase 2 Building Construction, Contract No. 6218.
Body
BE IT RESOLVED, that the improvements on Sayle Street Traffic Engineering Warehouse Building Phase 2 Building Construction have been completed on 9/16/09 be and are hereby accepted.  
 
Original Contract Sum      $     1,219,800.00
(Based on Actual Units)      $     1,219,800.00
Net Change by Change Orders      $          44,886.00 or 3.68%
Liquidated Damages      $                  0.00
Final Contract Amount      $    1,264,686.00
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. EP01-58310-810537-00-5833000       $126,469.00
Acc't. No. CB57-58310-810537                        $1,138,217.00