Improvements Accepted Priority Stump Removal - 2008, Contract No. 6232.
Body
BE IT RESOLVED, that the improvements on Priority Stump Removal - 2008 have been completed on November 14, 2008 and are hereby accepted.
Original Contract Sum $26,994.00
Final Contract Sum
(Based on Actual Units) $26,994.00
Net Change by Change Orders $9,226.84
Liquidated Damages $0.00
Final Contract Amount $36,220.84
Fiscal Note
Breakdown of costs by Acct. No.
CS53-54303-810581-00-00-53W0665 $36,220.84