Title: Amending the 2009 Capital Budgets of Engineering-Major Streets, Engineering-Other, Stormwater Utility and State Street-Capitol Square and Transferring Debt Proceeds Among Capital Projects.
Sponsors: David J. Cieslewicz
Attachments: 1. 2009 Budget Fix Updated Attachment.pdf
Fiscal Note
This resolution makes several needed technical adjustments to the 2009 capital budget for Engineering related projects.  One set of adjustments transfers $948,000 of unspent 2007 debt proceeds among various capital projects to allow the use of these available funds for previously approved purposes in compliance with Federal arbitrage regulations.  Another section rebalances budgets where actual project revenues exceeded budget estimates.  The final section removes budget authority that relates to the federal and state share of capital projects where these revenues and related expenditures are not recorded in the City's financial system.
 
No additional G.O. borrowing is required.  For the Stormwater Utility, there is a reduction in GO for 2009 of $204,930.
 
There is no anticipated impact upon the tax levy or cost controls.
 
Title
Amending the 2009 Capital Budgets of Engineering-Major Streets, Engineering-Other, Stormwater Utility and State Street-Capitol Square and Transferring Debt Proceeds Among Capital Projects.
Body
WHEREAS Federal Arbitrage law requires tax exempt debt proceeds to be spent within two years of issuance, which for the 2007 issuance is October 2009; and
 
WHEREAS the Stormwater Utility has $204,930 of unspent proceeds from the 2007 GO Debt issuance in the following project:
      Stormwater Basins (810384)                                    $204,930
 
WHEREAS the Stormwater Utility has the following project that could use these excess debt proceeds and thereby reduce the 2009 borrowing for this project:
      Wingra Creek (810268)                                    $204,930
 
WHEREAS Engineering-Major Streets has $743,410 of unspent proceeds from the 2007 GO Debt issuance in the following projects:
      Bridge Replacement/Repair (810356)                        $104,800
      Railroad Crossings (810357)                                    $85,600
      South High Point Road (810364)                              $524,770
      Beltline Frontage Rd (810371)                              $22,930
      Monona Dr (810506)                                          $5,310
 
WHEREAS Engineering-Major Streets has the following projects which could use $500,170 of these excess debt proceeds:
      
E Washington Ave (810370)                                    $150,000
            (City share of Segment 4 came in higher due to bids received)
      
Pleasant View Road (810507)                              $90,500
            (Prior phase of project that needs funds in order to be closed)
      
Pearson, Pierstoff and Wright (810522)                        $259,670
            (Assessments on State owned parcels were cancelled due to grant funding and
so the project needs these funds in order to be closed)
      
WHEREAS Engineering-Other has the following project which could use $224,650 of these excess debt proceeds:
      
Sidewalk Program (810376)                                    $224,650
            (To fully fund the planned sidewalk program for 2009)
 
WHEREAS State Street-Capitol Square has the following project which could use the remaining $18,590 of these excess proceeds:
      
Capitol Square Repairs (810286)                              $18,590
            (To provide sufficient resources to close this older project)
 
WHEREAS several Engineering projects have a budget authority which does not match available and projected funds due to actual revenues varying from budget estimates and therefore need to be corrected as follows:
      
Reconstruction Streets (810355): $725,170
      Bridges (810356): $95,000
      Railroad Crossings (810357): -$209,225
      Pavement Management (810358): $267,520
      Neighborhood Traffic Mgmt (810360): -$25,000
      Lien Road (810366): -$195,800
      East Washington (810370): $46,680
      Bikeways (810375): $64,000
      Sidewalks (810376): -$850,000
      Street ROW Landscaping (810377): $7,925
      Capital City Trail (810379): -$100,000
 
WHEREAS one Stormwater project has a budget authority which does not match available and projected funds due to actual revenues varying from budget estimates and therefore needs to be corrected as follows:
      
Inter-Municipal Stormwater (810392): $120,500
 
WHEREAS several Engineering capital projects that relate to Federal/State contracts have budget authority in excess of the local share and therefore needs to be reduced by the state/federal share of the cost as follows:
            
Bridges (810356): -$5,768,600      
      East Washington Ave (810370): -$15,960,000
      Bikeways (810375): -$50,000
      Sherman Flyer (810511): -$144,000
      Pleasant View/CTH M (810543) -$1,792,500
      Major Street Projects (810571): -$8,640,000
 
NOW THEREFORE BE IT RESOLVED that the unspent GO Debt proceeds be transferred as outlined above; and
 
BE IT FURTHER RESOLVED that the 2009 Capital Budgets of the Stormwater Utility, Engineering-Major Streets, Engineering-Other and State Street/Capitol Square be amended to reflect the items above.