File #: 10100    Version: Name: Substitute Resolution Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM on East Washington Avenue, Aberg Avenue, STH 30, and Commercial Ave (East Washington Avenue Segment 4).
Type: Resolution Status: Passed
File created: 4/23/2008 In control: BOARD OF PUBLIC WORKS
On agenda: 5/20/2008 Final action: 5/20/2008
Enactment date: 5/23/2008 Enactment #: RES-08-00525
Title: SUBSTITUTE - Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM on East Washington Avenue, Aberg Avenue, STH 30, and Commercial Ave (East Washington Avenue Segment 4). (15th & 17th ADs)
Sponsors: Joseph R. Clausius, Larry Palm
Title
SUBSTITUTE - Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM on East Washington Avenue, Aberg Avenue, STH 30, and Commercial Ave (East Washington Avenue Segment 4). (15th & 17th ADs)
Body


PREAMBLE

The reconstruction of East Washington Avenue between Blair Street and East Springs Drive is divided into 6 phases. The fifth phase of construction is referred to as Segment 4 and consists of East Washington Avenue at STH 30 and STH 30 / Aberg Avenue from the interchange at East Washington Avenue to just east of Fair Oaks Avenue. The work also includes replacing the pavement on Fair Oaks Avenue under STH 30 and the ramps near Fair Oaks Avenue to and from STH 30. The Construction of Segment 4 is planned for 2009.

Madison General Ordinance section 24.08(3) provides the Common Council the ability to allow construction activities outside of the hours of 7:00 AM to 7:00 PM. with the passage of a resolution and a hearing before the Board of Public Works. The construction of Segment 4 cannot be built between the hours of 7:00 AM and 7:00 PM because:

1. The amount of construction needed to complete the project exceeds the amount of production that a Contractor can reasonably be expected to achieve, even with the extra crews.

2. Sawcutting of concrete pavements after the pouring of the pavement must be done about 12 hours after the installation. The concrete must be hard enough to hold the machinery. The sawcutting must be done soon enough so that the sawcutting occurs before the pavement cracks.

3. Certain activities will disrupt live traffic lanes causing severe disruption and delay.

The proposed activities beyond the hours of 7:00 AM to 7:00 PM are as follows:

1. The sawing of concrete pavement. The timing of this activity is dependent on the rate at which the concrete cures. Sawing will be allowed at any time however the Contractor should avoid the hours of 10:00 PM to 7:00 AM when poss...