Madison, WI Header
File #: 07009    Version: 1 Name: Approving Plans and Specifications For Starkweather Creek Shoreline Improvements and Bike Path; and Plans and Specifications, and Schedule of Assessments for Clyde Gallagher Street Reconstruction Assessment District - 2007.
Type: Resolution Status: Passed
File created: 7/11/2007 In control: BOARD OF PUBLIC WORKS
On agenda: 8/7/2007 Final action: 8/7/2007
Enactment date: 8/8/2007 Enactment #: RES-07-00774
Title: Approving Plans and Specifications For Starkweather Creek Shoreline Improvements and Bike Path; and Plans and Specifications, and Schedule of Assessments for Clyde Gallagher Street Reconstruction Assessment District - 2007. (15th AD)
Sponsors: Common Council By Request
Attachments: 1. 53W0223 ClydeG 07 06 07.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsWatch
8/7/20071 COMMON COUNCIL Adopt and Close the Public HearingPass Action details Meeting details Not available
7/30/20071 Finance Dept/Approval Group Approved Fiscal Note By The Comptroller's Office  Action details Meeting details Not available
7/19/20071 Engineering Division Fiscal Note Required / Approval  Action details Meeting details Not available
7/18/20071 BOARD OF PUBLIC WORKS RECOMMEND TO COUNCIL TO ADOPT - PUBLIC HEARINGPass Action details Meeting details Not available
Fiscal Note
*The availability of funds in 810354 (Assessable Streets) is contingent on the adoption of File ID 06141.

Funds are available in Acct. Nos.
CS53-58255-810375-00-53W0223 (Bridges) $151,200
CS53-58240-810375-00-53W0223 (Bike Paths) $396,000
ESTM-58290-810394-00-53W0223 (Shoreline) $387,100
ESTM-58270-810551-00-53W0223 (Urban BMP) $ 40,000
CS53-58250-810354-00-53W0223 (Assessable Str.) $ 50,000
ESTM-58270-810381-00-53W0223 (Storm Sewer) $265,500
ES01-58275-810332-00-53W0223 ( Sanitary Sewer) $334,000
EW01-58273-810455-00-53W0223 ( Water Main) $ 86,400

Total $1,710,200
Assessments $ 36,000
City Cost $1,674,200
Title
Approving Plans and Specifications For Starkweather Creek Shoreline Improvements and Bike Path; and Plans and Specifications, and Schedule of Assessments for Clyde Gallagher Street Reconstruction Assessment District - 2007. (15th AD)
Body
The City of Madison is planning to improve the Starkweather Creek corridor from Milwaukee Street to Darbo Drive by reconstructing the creek shoreline, reconstructing segments of Clyde Gallagher Street (west side of the creek) and constructing a paved bike path along the remainder of the corridor. The creek restoration includes removal of existing sheet piling, minor dredging and restoration of banks with a combination of riprap, cut stone and native plantings. The street reconstruction will replace the existing sub-standard street with a standard pavement section with curb & gutter and concrete sidewalk on one side. Two segments of existing Clyde Gallagher Street will be removed and a new bike / pedestrian bridge over the creek will be constructed, providing a continuous bikeway for the length of the corridor. Sachs Street will be terminated in a cul-de-sac. The project also includes replacement of sanitary sewer from Milwaukee Street to Marquette Street near Darbo Drive and a force main crossing of the creek. Project also includes replaceme...

Click here for full text