Fiscal Note
The proposed resolution approves plans, specifications, and assessments and authorizes the Board of Public Works to advertise and receive bids for the Meyer Avenue Assessment District - 2025. The total estimated cost of the project is $2,084,393.40 comprised of $1,661,052.97 in City costs, $101,304 in Wisconsin Department of Natural Resources GI Pilot Study grant funding, and $322,036.43 in assessments. Funding is available in the 2025 Adopted Capital Budgets for Engineering - Major Streets (Munis #15219 - $2,026,893.40) and Stormwater Utility (Munis #15465/#12930 - $57,500) No additional appropriation is required.
Title
Approving Plans, Specifications, And Schedule Of Assessments For Meyer Avenue Assessment District - 2025 (District 11).
Body
The Board of Public Works and the City Engineer having made reports of all proceedings in relation to the improvement of Meyer Avenue Assessment District - 2025 pursuant to a resolution of the Common Council, RES-24-00680, ID No. 85901, adopted 11/26/24, which resolution was adopted thereto, and the provisions of the Madison General Ordinances and the Wisconsin Statutes in such case made and provided, and the Common Council being fully advised.
BE IT RESOLVED:
1. That the City at large is justly chargeable with and shall pay the sum of $1,661,052.97of the entire cost of said improvement.
2. That for those eligible property owners requesting construction of a rain garden in the public right-of-way adjacent to their property shall execute the necessary waiver of special assessments on forms provided by the City Engineer;
3. That the sum assigned to each separate parcel, as indicated on the attached schedule of assessment, is hereby specially assessed upon each such parcel.
4. That the Common Council determines such special assessments to be reasonable.
5. That the work or improvement be carried out in accordance with the reports as finally approved.
6. That such work or improvement represents an exercise...
Click here for full text