File #: 94662    Version: 1 Name: Change Order No. 1 to Contract 9709, Yahara Hills Golf Course Paved Paths, to Parisi Construction Co, LLC, for $2,500.00 and a time extension to a completion date of 10/16/26.
Type: Miscellaneous Status: In Committee
File created: 9/4/2026 In control: BOARD OF PUBLIC WORKS
On agenda: Final action:
Enactment date: Enactment #:
Title: Change Order No. 1 to Contract 9709, Yahara Hills Golf Course Paved Paths, to Parisi Construction Co, LLC, for $2,500.00 and a time extension to a completion date of 10/16/26. (District 16)
Attachments: 1. CO1 - 9709.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsWatch
No records to display.

Title

Change Order No. 1 to Contract 9709, Yahara Hills Golf Course Paved Paths, to Parisi Construction Co, LLC, for $2,500.00 and a time extension to a completion date of 10/16/26. (District 16)

Body

See Attached