Title: Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM for work associated with City of Madison public works projects #15045 Lake Street Sanitary Sewer Replacement & #14145 State Street Campus Garage Mixed-Use Project. (District 2 and District 8)
Sponsors: MGR Govindarajan, Juliana R. Bennett
Attachments: 1. 9501 Public Hearing Letter.pdf
Fiscal Note
No Funds Required.
Title
Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM for work associated with City of Madison public works projects #15045 Lake Street Sanitary Sewer Replacement & #14145 State Street Campus Garage Mixed-Use Project. (District 2 and District 8)
Body
As part of the Lake Street Sanitary Replacement and State Street Campus Garage Replacement project, work associated with these two projects does not allow for all construction activities in this area to occur during the normal working hours of 7:00AM and 7:00PM. Contractors for both projects require additional time outside of normal working hours to complete the projects in a timely manner.

Madison General Ordinance section 24.08(3) provides the Common Council the ability to allow construction activities outside of the hours of 7:00 AM to 7:00 PM with the passage of a resolution and a hearing before the Board of Public Works.

The proposed activities beyond the hours of 7:00 AM to 7:00 PM are as follows:

1. Excavation, shoring of trenches, replacement of sanitary sewer main, backfill and compaction of the excavation trench, and restoration of pavement along N. Lake Street.
2. Bypassing pumping of sanitary wastewater flows around the sanitary replacement construction work area.
3. Pouring of concrete walls and floor slabs at 415 N. Lake Street.

NOW THEREFORE BE IT RESOLVED, that construction work, with associated noise impacts, between the hours of 7:00 PM to 7:00 AM at the intersection of University Ave and N. Lake Street along with the 400 block of N. Lake Street, are hereby approved in accordance with Section 24.08(3) of the Madison General Ordinances., and

BE IT FURTHER RESOLVED, that the construction activities outside the hours of 7:00 AM to 7:00 PM are limited to those activities identified in this resolution and the hours specified, and

BE IT FURTHER RESOLVED, that the approval of that construction work, as p...