Title
Improvements accepted for E. Main Street Reconstruction Assessment District - 2005, Contract No. 5835. (6th AD)
Body
BE IT RESOLVED, that the street improvements on E. Main Street Reconstruction Assessment District - 2005 have been completed on 12/03/05 be and are hereby accepted.
Original Contract Sum $ 554,803.80
(Based on Actual Units) $ 540,576.67
Net Change by Change Orders $ 25,639.30 or 4.62%
Liquidated Damages $ 6,982.50
Final Contract Amount $ 559,233.47