Fiscal Note
Breakdown of costs by account number:
Acc't. No. CS53-58250-810274-00-53B0918 $195,983.80
Acc't. No. CW53-58270-810274-00-53B0918 $112,586.57
Acc't. No. ES01-58275-810274-00-53B0918 $379,221.61
Acc't. No. EW01-58273-810455-00-53B0918 (#5882) $103,151.52
Title
Improvements accepted for Northeast Industrial Area Assessment District - Phase I, Contract No. 5428. (17th AD)
Body
BE IT RESOLVED, that the street, water, and storm and sanitary sewer improvements on Northeast Industrial Area Assessment District - Phase I have been completed on 12/19/03 be and are hereby accepted.
Original Contract Sum $ 844,580.25
(Based on Actual Units) $ 748,245.88
Net Change by Change Orders $ 42,697.62 or 5.05%
Liquidated Damages $ 0.00
Final Contract Amount $ 790,943.50