Legislation Details

File #: 94990    Version: 1 Name: Accepting sanitary sewer, storm sewer, public stormwater management improvements, and street improvements (including bituminous surface pavement) constructed by Private Contract in The Willows, Private Contract No. 2428.
Type: Resolution Status: Items Referred
File created: 9/24/2026 In control: BOARD OF PUBLIC WORKS
On agenda: 10/20/2026 Final action:
Enactment date: Enactment #:
Title: Accepting sanitary sewer, storm sewer, public stormwater management improvements, and street improvements (including bituminous surface pavement) constructed by Private Contract in The Willows, Private Contract No. 2428 (District 9).
Sponsors: BOARD OF PUBLIC WORKS
Attachments: 1. The Willows Sanitary Schedule A Unit Cost.pdf, 2. The Willows Storm Schedule A Unit Cost.pdf, 3. 2428 Street Schedule A complete.pdf, 4. 2428 SWM Schedule A.pdf
Fiscal Note
No City Funds required. Private contract.
Title
Accepting sanitary sewer, storm sewer, public stormwater management improvements, and street improvements (including bituminous surface pavement) constructed by Private Contract in The Willows, Private Contract No. 2428 (District 9).
Body
WHEREAS, TRMCKENZIE, INC., has satisfactorily completed the installation of sanitary sewer, storm sewer, public stormwater management improvements, and street improvements (including bituminous surface pavement) by private contract, in accordance with the City of Madison Standard Specifications for Public Works Construction, in: The Willows.

NOW, THEREFORE, BE IT RESOLVED

1. That said sanitary sewer, storm sewer, public stormwater management improvements and street improvements (including bituminous surface pavement) be and are hereby accepted.

2. That said sanitary sewer improvements are hereby assigned to the Madison Sewer Utility for ownership and maintenance and that the attached Schedule "A" representing the actual cost of construction of these improvements shall be reflected in the Madison Sewer Utility's "Utility Plant In Service".

SANITARY SEWER ACCOUNTING DATA

A) Total Contract Value (including Engineering
and Miscellaneous Costs) $ 157,724.94

B) Contributions in Aid of Construction:
a) Public Sewer Components $ 157,724.94
b) Sewer Laterals $ ____-0-

C) Investments in Capital (MSU Share) $ ____-0-

D) Total Plant Value $ 157,724.94

3. That said storm sewer improvements are hereby assigned to the Madison Storm Water Utility for ownership and maintenance and that the attached Schedule "A" representing the actual cost of construction of these improvements shall be reflected in the Madison Storm Water Utility's "Utility Plant In Service".

Increase in Total Plant Value per Schedule “A” $297,029.24.


4. That said stormwater management improvements on OL 1 are hereby assigned to the Madison Storm Water Utility for ownership and mai...

Click here for full text