Fiscal Note
The proposed resolution would award the contract for East Towne Detention Basin Improvement at an estimated cost of $1,283,040 including contingency. Funding is available in Munis project #11066. No additional appropriation is required.
Title
Awarding Public Works Contract No. 9437, East Towne Detention Basin Improvements. (17th AD)
Body
BE IT RESOLVED, that the following low bids for miscellaneous improvements be accepted and that the Mayor and City Clerk be and are hereby authorized and directed to enter into a contract with the low bidder contained herein, subject to the Contractor's compliance with Section 39.02 of the Madison General Ordinances concerning compliance with the Affirmative Action provisions and subject to the Contractor's compliance with Section 33.07 of the Madison General Ordinances regarding Best Value Contracting:
BE IT FURTHER RESOLVED, that the funds be encumbered to cover the cost of the projects contained herein.
See attached document (Contract No. 9437) for itemization of bids.