Title
Improvements accepted for East Main Street, South Livingston Street Reconstruction Street Assessment District - 2002, Contract No. 5527. (6th AD)
Body
BE IT RESOLVED, that the street, water main, and storm and sanitary sewer improvements on East Main Street, South Livingston Street Reconstruction Street Assessment District - 2002 have been completed on 8/4/07 be and are hereby accepted.
Original Contract Sum $ 662,493.90
(Based on Actual Units) $ 591,058.01
Net Change by Change Orders $ 0.00 or 0.00%
Liquidated Damages $ 14,725.00
Final Contract Amount $ 576,333.01
Fiscal Note
Breakdown of Costs by account numbers:
Acc't. No. CS53-58250-810355-00-53B0570 $266,255.72
Acc't. No. ESTM-58270-810381-00-53B0570 $77,303.68
Acc't. No. ES01-58275-810332-00-53B0570 $117,829.52
Acc't. No. EW01-58273-810455-00-53B0570 $114,944.09