Improvements accepted for Midvale Blvd., Tokay Blvd., & Waite Circle Resurfacing Assessment District, Contract No. 6370.
Body
BE IT RESOLVED, that the improvements on Midvale Blvd., Tokay Blvd., & Waite Circle Resurfacing Assessment District have been completed on 11/19/09 be and are hereby accepted.
Original Contract Sum $ 1,922,172.05
(Based on Actual Units) $ 1,869,459.47
Net Change by Change Orders $ 75,111.70 or 3.91%
Liquidated Damages $ 990.00
Final Contract Amount $ 1,943,581.17