Improvements accepted for Siggelkow Road Reconstruction Street Assessment District - 2008, Contract No. 6112.
Body
BE IT RESOLVED, that the improvements on Siggelkow Road Reconstruction Street Assessment District - 2008 have been completed on 11/14/08 be and are hereby accepted.
Original Contract Sum $ 1,782,529.05
(Based on Actual Units) $ 1,830,299.98
Net Change by Change Orders $ 12,046.90 or 0.68%
Liquidated Damages $ 0.00
Final Contract Amount $ 1,842,346.88