Title: Awarding Public Works Contract No. 9336, Felland Reservoir Booster Pump Install Milky Way Reservoir Valve Install. (District 3)
Sponsors: BOARD OF PUBLIC WORKS
Attachments: 1. 9336BidOpeningTab.pdf, 2. 9336.pdf

Fiscal Note

The proposed resolution authorizes awarding the contract for the Felland Reservoir Booster Pump Install Milky Way Reservoir Valve Install at a total estimated cost of $161,860 including contingency. Funding for the project is available in Munis #14413. No additional appropriation is required.

Title

Awarding Public Works Contract No. 9336, Felland Reservoir Booster Pump Install Milky Way Reservoir Valve Install. (District 3)

Body

BE IT RESOLVED, that the following low bids for miscellaneous improvements be accepted and that the Mayor and City Clerk be and are hereby authorized and directed to enter into a contract with the low bidder contained herein, subject to the Contractor's compliance with Section 39.02 of the Madison General Ordinances concerning compliance with the Affirmative Action provisions and subject to the Contractor's compliance with Section 33.07 of the Madison General Ordinances regarding Best Value Contracting:

 

BE IT FURTHER RESOLVED, that the funds be encumbered to cover the cost of the projects contained herein.

 

See attached document (Contract No. 9336) for itemization of bids.