Fiscal Note
Budget authority is available in CS53-58250-810571-00-53W0891 "Major Street Projects" $14,000
Total cost : $14,000
Special Assessments: $4,000
City share: $10,000
Title
Approving Plans, Specifications, and Schedule of Assessments for 115 King Street Vault Assessment District - 2011.
Body
The Board of Public Works and the City Engineer having made reports of all proceedings in relation to the improvement of 115 King Street Vault Assessment District - 2011 pursuant to a resolution of the Common Council, ID No. 23615 which resolution will be adopted on 9/6/11 in accordance with Sec. 66.0701 (formerly Sec. 66.62) of the Wisconsin Statutes and Sec. 4.09 of the Madison General Ordinances and having in all things duly conformed to the order of the Common Council in relation thereto, and the provisions of the Madison General Ordinances and the Wisconsin Statutes in such case made and provided, and the Common Council being fully advised.
BE IT RESOLVED:
1. That the City at large is justly chargeable with and shall pay the sum of $10,000.00 of the entire cost of said improvement, and that the sum assigned to each separate parcel, as indicated on the attached schedule of assessment, is hereby specially assessed upon each such parcel.
2. That the Common Council determines such special assessments to be reasonable.
3. That the work or improvement be carried out in accordance with the reports as finally approved.
4. That such work or improvement represents an exercise of the police power of the City of Madison.
5. That the plans & specifications and schedule of assessments in the Report of the Board of Public Works and the Report of the City Engineer for the above named improvement be and are hereby approved, and that the center line grades for the above named improvement be and are hereby established.
6. That the Board of Public Works be and is hereby authorized to advertise for and receive bids for the said improvements.
7. That no advertisement for b...