Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58250-810355-00-53B0693 $185,260.74
Acc't. No. ESTM-58270-810381-00-53B0693 $101,039.93
Acc't. No. ES01-58275-810332-00-53B0693 $143,308.31
Acc't. No. EW01-58273-810455-00-53B0693 $153,110.20
Title
Improvements accepted for Chapman Street & Mandan Circle Reconstruction Assessment District, Contract No. 5607. (10th AD)
Body
BE IT RESOLVED, that the street, water main, and storm and sanitary sewer improvements on Chapman Street & Mandan Circle Reconstruction Assessment District have been completed on 11/04/06 be and are hereby accepted.
Original Contract Sum $ 740,267.25
(Based on Actual Units) $ 586,369.18
Net Change by Change Orders $ 3,000.00 or 0.40%
Liquidated Damages $ 6,650.00
Final Contract Amount $ 582,719.18