Fiscal Note
Funds are available in Acct. Nos.:
CS53-58260-810358-00-53W0403 (pulverize & pvmt) $3,557,600
CS53-54996-810358-00-53W0403 (mill & pvmt) $25,000
CS53-54996-810358-00-53W0403 (casting) $700,000
ESTM-58270-810381-00-53W0403 (stormwater) $275,000
ES01-58275-810332-00-53W0403 (san. swr) $138,400
EW01-58273-810455-00-53W0403 (water dept) $694,200
CE57-58540-810417 (traffic eng) $9,500
ET01-56532-502360 (metro bus) $2,000
Acct. Nos. Totals $5,401,700
Project total estimated cost is $5,401,700 (City cost $4,851,200)
Title
AMENDED - Approving Plans, Specifications, And Schedule Of Assessments For Curb and Gutter in Conjunction w/Resurfacing - 2007 Assessment District. (City-Wide)
Body
The Board of Public Works and the City Engineer having made reports of all proceedings in relation to the improvement of Curb and Gutter in Conjunction w/Resurfacing - 2007 Assessment District pursuant to a resolution of the Common Council, ID No. 05315, adopted 1/16/07, which resolution was adopted in accordance with Sec. 66.0701 (formerly Sec. 66.62) of the Wisconsin Statutes and Sec. 4.09 of the Madison General Ordinances and having in all things duly conformed to the order of the Common Council in relation thereto, and the provisions of the Madison General Ordinances and the Wisconsin Statutes in such case made and provided, and the Common Council being fully advised.
BE IT RESOLVED that Plymouth Circle, Priscilla Lane and Larkin Street be removed from the list of street resurfacing schedule of assessments and refer them to the Board of Public Works to coordinate with reservoir park water well drilling.
BE IT RESOLVED:
1. That the City at large is justly chargeable with and shall pay the sum of $4,851,200 of the entire cost of said improvement, and that the sum ...
Click here for full text