Madison, WI Header
File #: 85460    Version: 1 Name: Authorizing the Mayor and the City Clerk to execute a contract between the City of Madison and MSA Professional Services, Inc. for design engineering services for S High Point Road from Midtown Meadows Plat to Raymond Rd.
Type: Resolution Status: Passed
File created: 10/1/2024 In control: Engineering Division
On agenda: 10/29/2024 Final action: 10/29/2024
Enactment date: 11/1/2024 Enactment #: RES-24-00630
Title: Authorizing the Mayor and the City Clerk to execute a contract between the City of Madison and MSA Professional Services, Inc. for design engineering services for S High Point Road from Midtown Meadows Plat to Raymond Rd (District 1 and District 7)
Sponsors: John W. Duncan, Nasra Wehelie
Attachments: 1. HPR_proposal_evaluation_report.pdf

Fiscal Note

The proposed resolution authorizes awarding the contract for the reconstruction of S High Point Road from Midtown Meadows Plat to Raymond Rd in 2026 at a total estimated cost of $285,000, including contingency. Funding for the project is

available in Munis #12454. No additional appropriation is required.

 

Title

Authorizing the Mayor and the City Clerk to execute a contract between the City of Madison and MSA Professional Services, Inc. for design engineering services for S High Point Road from Midtown Meadows Plat to Raymond Rd (District 1 and District 7)

Body

PREAMBLE

 

The City of Madison is proposing to reconstruct S High Point Road from Midtown Meadows Plat to Raymond Rd in 2026.  The project includes construction of the roadway, sidewalk/multiuse path, lighting, stormwater facilities, sanitary sewer and water main. The City desires to enter into an agreement with a consultant for design engineering services.

 

Pursuant to City Ordinances and Policies, the City Engineer advertised for consultant proposals, reviewed the submitted proposals, and recommends the design engineering contract be awarded to MSA Professional Services, Inc.  The consultant’s services will include the completion of preliminary plans and the Environmental Assessment report and Final Plans & Specifications. 

 

This will be a multi-year design project (2024-2025) and construction is scheduled for 2026. 

 

NOW THEREFORE BE IT RESOLVED that the Mayor and City Clerk are hereby authorized to execute an agreement with MSA Professional Services, Inc. for design engineering services for S High Point Road from Midtown Meadows Plat to Raymond Rd.