Improvements accepted for Sidewalk & Curb & Gutter, Citywide Installation & Repair - 2008, Contract No. 6103.
Body
BE IT RESOLVED, that the improvements on Sidewalk & Curb & Gutter, Citywide Installation & Repair - 2008 have been completed on 11/15/08 be and are hereby accepted.
Original Contract Sum $ 313,850.00
(Based on Actual Units) $ 267,203.41
Net Change by Change Orders $ 55,830.81 or 17.78%
Liquidated Damages $ 0.00
Final Contract Amount $ 323,034.22
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-54473-810376-00-53W0526 $147,571.01
Acc't. No. CS53-58280-810376-00-53W0526 $66,921.41
Acc't. No. CS53-54472-810358-00-53W0526 $90,233.64
Acc't. No. CS53-54472-810360-00-53W0526 $18,308.16