Improvements accepted for Greenway Tree Removals - 2005, Contract No. 5858. (Various ADs)
Body
BE IT RESOLVED, that the improvements on Greenway Tree Removals - 2005 have been completed on 12/09/06 be and are hereby accepted.
Original Contract Sum $ 37,250.00
(Based on Actual Units) $ 37,249.75
Net Change by Change Orders $ 7,936.05 or 21.30%
Liquidated Damages $ 0.00
Final Contract Amount $ 45,185.80
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. ESTM-58270-810382-00-53W0268 $45,185.80