Title
Improvements accepted for Yahara River Parkway Path, Contract No. 5940.
Body
BE IT RESOLVED, that the improvements on Yahara River Parkway Path have been completed on 11/9/06 be and are hereby accepted.
Original Contract Sum $ 138,091.00
(Based on Actual Units) $ 132,565.73
Net Change by Change Orders $ 17,149.80 or 12.41%
Liquidated Damages $ 0.00
Final Contract Amount $ 150,541.45
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58240-810546-00-53W0331 $150,541.45